Watergate at Landmark's own directions page puts the drive home in one line: from I-395, take exit 3B to Duke Street toward Landmark, turn right onto S. Walker Street, right onto Stevenson Avenue, then take the second left onto Yoakum Parkway. That first step, the exit from northbound I-395 onto eastbound Duke Street, is now an active City of Alexandria construction project.
The redesign is built around a destination that doesn't exist yet. The City says the ramp changes are needed so emergency vehicles have direct access to the new Inova hospital complex planned for the former Landmark Mall site. It also expects more traffic once the new development opens. The ramp is also the first of three projects lined up for the same short stretch of Duke Street, and each runs on its own schedule.
What the Bottom of the Ramp Looks Like Now
In its March 5, 2026 community meeting, the City listed the existing conditions it wants to fix. Its slide on today's ramp lists:
- A one-lane ramp onto Duke Street
- Heavy traffic flow
- A concrete median separating the lanes
- No direct access to the left-turn lane
- A busy right turn at Walker Ln
- Pedestrian access to eastbound Duke Street
The project has three stated goals: cut down conflicts between drivers already on Duke Street and drivers coming off I-395, give northbound I-395 traffic direct access to the proposed Inova site, and improve safety. Today, someone heading for the Landmark site leaves the interstate in the same single lane as everyone else, and that lane has no direct way to reach the left-turn lane. The rebuild adds one.
What Gets Built
The approved design on the City's project page has eight labeled parts:
- New retaining wall
- New vegetation
- New guardrail
- New concrete sidewalk
- New pedestrian crossing
- New traffic signal
- New raised concrete median
- New raised concrete curb
The meeting deck shows how they fit together. The ramp gets direct access to the turn lane and a new traffic signal, and the slide labels access to the West End development and the proposed Inova site. The existing noise barrier stays where it is. For anyone who walks this stretch, the new sidewalk and crosswalk matter as much as the signal, because the deck lists pedestrian access to eastbound Duke as one of the existing conditions.
The money is listed two different ways. The deck breaks costs into $1.5 million for design, $4.6 million for construction and $1 million for inspection, all paid from the City's Capital Improvement Program. The project page lists a total budget of $11,750,000.
The Hours, the Lanes and the Clock
For a resident, the construction plan matters more than the finished drawing. The City has committed to the following:
| What | The City's plan |
|---|---|
| The I-395 ramp | One lane open at all times; no full ramp closure required |
| Duke Street | Stays open throughout construction, with some delays and flaggers when needed |
| Sidewalks | Occasional detours, with alternative pathways provided |
| Construction vehicles | More trucks entering the site from I-395 and Duke Street |
| Work hours | Monday to Friday, 9 a.m. to 3:30 p.m. |
| Holidays | No construction |
| Projected completion | January 2028 |
The 9 a.m. to 3:30 p.m. window falls between the two rush hours. Someone who drives this ramp at 8 a.m. or 5:30 p.m. on a weekday should run into lane-closing work far less often than someone running errands midday.
The schedule has already moved once. The March deck set site activation for April 2026. The City's project page, last updated Monday, June 1, says construction "is starting" and that crews would run a mobile survey that week. It warns of intermittent lane closures and stopped vehicles on the ramp and on eastbound Duke Street. The page's schedule block shows construction from August 2025 to August 2028. Its "Site Activity" line reads April 2028 to January 2028, which can't be right as printed. Take January 2028 as the City's target, not a promise.
The Sidewalk Outside, on Its Own Schedule
The second project starts where the ramp work stops. Access Improvements at Landmark is a pedestrian project, and its official description reads like a map of the blocks between Watergate and the Landmark site. VDOT's environmental document describes three pieces: about 900 linear feet of 7-foot-wide sidewalk on the south side of Duke Street between Walker Lane and Van Dorn Street, about 2,300 linear feet of 7-foot-wide sidewalk on the east side of North Van Dorn Street from the Duke Street ramp to Holmes Run Parkway, and about 1,200 linear feet of 12-foot-wide multi-use trail along the west side of Van Dorn. The public notice also calls for retrofitting the northbound lanes of the Van Dorn bridge over Duke Street to fit a wide sidewalk and safety fencing.
The City's project page adds more crosswalks and pedestrian signals, ADA curb ramps, guardrails, lighting and relocated stormwater inlets. When the 30% plans went out for VDOT review in 2026, the comment period closed with two comments and no requests for a formal public hearing. The City and VDOT then said they would move ahead with final design.
The timing is where the two projects overlap. Design runs from October 2025 to May 2027, and construction is scheduled from March 2027 to August 2029. If both projects stay on schedule, sidewalk crews would start on Duke and Van Dorn about ten months before the ramp contractor's January 2028 target. The south side of Duke would then have two separate work zones, run under two different contracts, for most of 2027.
The Bus Corridor Without a Settled Finish
The third project is the biggest and has the least settled schedule. The Duke Street Transitway is a planned 4.5-mile high-capacity bus corridor from the West End Transit Center at Landmark to the King Street Metro, with sidewalk, bike path and streetscape connections along the way. As ALXnow reported in April, the City's funding request for the Van Dorn interchange area describes rebuilding interchange ramps east of Van Dorn, filling a missing sidewalk segment under the Van Dorn overpass, and adding a dedicated transit lane plus a new signal for westbound Duke Street traffic turning toward Van Dorn.
The published dates don't agree. The City's Duke Street in Motion page expected final design in spring 2027, permits by mid-2027 and construction soon after. The City's approved FY 2027 to 2036 capital plan has construction starting in FY 2028. The Northern Virginia Transportation Authority's dashboard lists the transitway at $102.555 million with an anticipated completion date of December 31, 2029. A City display board from April 2026 shows design from spring 2026 to spring 2028 and construction from 2029 to 2031. In other words, today's official estimates for when this corridor is finished span about two years.
The western end of that corridor is already in use. Since November 2, 2025, DASH Lines 30, 32 and 35 and Metrobus A25, A28, F23 and F24 have boarded at the West Alexandria Transit Center, ALXnow reported, and Metrobus A29 was scheduled to join on December 15, 2025. The capital plan describes the permanent transit center as having at least six bays, with construction slated to begin in FY 2028. DASH's current schedule shows Line 30 running from Van Dorn Metro along Duke Street to King Street and Braddock, every 10 to 20 minutes at weekday peak and every 30 minutes off-peak. Line 32 connects Landmark, Van Dorn Metro, Eisenhower Valley and King Street every 30 minutes.
The three schedules overlap. The ramp work began this year with a January 2028 target. The sidewalk work is scheduled from March 2027 to August 2029. The transitway's construction window, depending on which document you read, starts in FY 2028 and runs as late as 2031. All three exist to serve the hospital site and the transit hub next door. For Watergate residents, the result is a Duke Street frontage that will see some kind of active construction for several years.
Tonight at Minnie Howard
The City is hosting a West End transportation open house today, Thursday, October 29, from 5 to 8 p.m. at the Minnie Howard Campus. The City's announcement lists all three projects in this post, I-395 at Duke Street, Access Improvements at Landmark and the West End Transitway, along with the South Van Dorn Street Bridges, King Street-Bradlee and the West End high-crash intersection safety audits. City staff will be there to share project status and timelines and answer questions. Updates are available through the West End Open House page. Free interpretation and translation are available by emailing [email protected] or calling 703.746.3960.
If you have a question about the ramp itself, the City lists H. Demond Frazier, the project's technical project manager, at 703.746.4632.
Here at Paul Gonzalez, we follow the Duke Street projects closely because Watergate at Landmark is where much of our work happens. If you're a neighbor wondering how construction at the end of the drive home could play into a sale or a purchase over the next few years, we're glad to walk through the timelines with you. Let's Connect.